Management Plan June to October 2005
Phase I Parking Lot Design, Permitting, Construction Documents February to June 2006
Phase I Parking Lot Construction September 2006 to July 2007
Phase IIA Design and Permitting August 2015 to March 2016
Phase IIA Volunteer work parties, trail construction Started April 2016