Pavement Management Program

2013 Construction Schedule

Below is a general schedule showing the paving contractors order of work by site location. Please be aware that this schedule is highly dependent on weather. As work gets closer in each neighborhood, the contractor will be posting no parking signs. The time restrictions for parking are typically 7:00 am to 5:00 pm, Monday through Friday.

Current Major Work Locations:
    Timberline Neighborhoods

Current Work:  
    Preparation work for paving; pavement grinding and patching.
    Paving is anticipated to start the week of August 26

                      

 Anticipated Start Date

 Location/Neighborhood

 Remaining Work

 June 24th

 Murmuring Firs

 Shoulder gravel, utility adjustments

 July 8th

 Pacific Estates

 Shoulder gravel, pavement markings, utility adjustments

 July 15th

 The Country

 Shoulder gravel, pavement markings, utility adjustments

 July 15th

 Hampton Woods Div. 1

 utility adjustments

 July 15th

 Hampton Woods Div. 2

 utility adjustments

 July 22nd

 Evans Creek

 utility adjustments

 August 8th

 Louis Thompson Road

 

 August 19th

 Timberline Highlands

 

 August 19th

 Timberline Park

 

 August 19th

 Timberline 1-5

 

 

 NE 25th Way

 

General Information:

Hours of work will be between 7:00 am and 5:00 p.m. daily.

Driveway Access on most streets will remain open throughout most of the construction but traffic will be reduced to sharing a lane controlled by flaggers. In cul-de-sacs, crews will work with the residents to temporarily close the cul-de-sac so that paving operations can be completed quickly. During the actual paving process, there is typically a two to three hour time period where access to driveways is not allowed. This is time needed for the pavement to cool and harden before traffic can drive on it.

On Street Parking on the days of construction, on-street parking will need to be restricted. Signs will be posted in advance of the work to notify residents of the parking restrictions.

Waste and Recycling Schedule is not changed due to construction. When days of paving and waste collection coincide, we work with the collection service to adjust their route schedule and focus first on the streets that are being paved. If there is construction in your neighborhood, please be sure to have your waste and recycling out extra early.

Tree Trimming may need to be done in front of your house. If there is vegetation in front of your property that extends out into the street, it will need to be pruned back to allow the equipment to do the street resurfacing. Please trim the vegetation along your property if this is the case. City crews or the Contractor will trim vegetation as needed for the project. However, they will only be doing the minimum needed to clear the road for paving and some additional trimming may need to be completed afterwards by the adjacent property owner.

Street Cuts - Ordinance # 02001-78 prohibits the excavation of overlayed or newly constructed roads for a minimum of five years following construction or paving. If you are planning to have any underground utility work done, such as water, sewer, telephone, gas, electrical, etc., you are strongly encouraged to expedite this work if it involves utility work under the new pavement. Please call us as soon as possible to coordinate this work.

If you have any questions about the construction please call or email Jim Grueber.