Summary
The NE Inglewood Hill Road Non-Motorized Project, 216th Avenue NE to 222nd Avenue NE, proposes 2,000-feet of sidewalk and widened sidewalk for bicycles on the south side of the road. To acomodate the widening, retaining walls, safety railing, and storm drain improvements will also be included.
Project Updates
Goals and Benefits
Connects existing pedestrian facilities between 216th Avenue NE and 222nd Avenue NE, closing a gap that leads into the City's commercial core and the new Rec Center. New neighborhoods along the Inglewood and 216th Avenue NE corridor will benefit by this connectivity.
Timeline
Design: February - May, 2012
Construction: summer 2012.
Budget
$1,050,000 is budgeted in the Transportation Capital Fund.
Public Involvement
A public Open House we be held for residents to share information and provide feedback on this project.
Date: Wednesday, February 29, 2012
Time: Drop by anytime between 6-7:30 p.m.
Location: Boys and Girls Club Recreation Center (old library)
825 - 228th Avenue NE, Sammamish 98074
Permits, Environmental Review