244th Ave SE Non-Motorized Improvements, SE 32nd Street to SE 24th Street

Click here to sign up and receive email updates on this project.

Summary

The 244th Avenue SE Non-Motorized Project proposes to construct 2,600-feet of sidewalk, bike lane, and planter strip on the east side of the road.  Retaining walls, safety fencing, and storm drain improvements will also be included to accomodate the design.  See the proposed typical cross section below:

Project Updates    

*Update - Paving Thursday, April 10. Expect delays. Use alternate routes if possible. Driveways off 244th Ave SE may have access restricted (up to 30-minutes) between 8 AM and 6 PM. Need vehicle access during temporary restriction? Please seek permission from the flagger.

Paving may extend into Friday. Lane lines will be striped next week. Questions? Please call the project manager at (425) 495-2751.

Goals and Benefits

Will provide facilities for pedestrians and bicyclists on 244th Avenue SE adjacent Beaver Lake Park, from SE 32nd Street to SE 24th Street.

Timeline

Open House - Tuesday, September 18, 2012 (see notice below)

Design Phase - January 2013

Construction Begins:   August 26, 2013
Construction Ends:  April 2014

Budget

 Construction: $1,915,938

Public Involvement

Permits, Environmental Review

 

Staff Contact

News releases

Bid Results - 244th Ave NE Non-Motorized Project, Stage 2 Mar. 29, 2012