212th Ave SE Improvements
Summary
This project creates new sidewalk and landscape planter strip on the west side of 212th Ave SE between SE 24th and the Crossings at Pine Lake subdivision. Also, both sides of the street will receive widened shoulders to accommodate bicyclists.
Project Updates
Construction is complete. The project is now under the maintenance and monitoring of the wetland and stream buffer mitigation planting.
Goals and Benefits
The project extends sidewalk from The Crossings at Pine Lake subdivision south to SE 24th Street where it will connect with existing soft pedestrian paths. Additionally, the narrow shoulders will be widened to accommodate bicycles.
Timeline
Construction Start: July 17, 2017
Physical Completion: November 9, 2017
Budget
$748,000 (through construction)
Public Involvement
See the "Comment" hotlink at left, or "Subscribe" hotlink above the summary.
Permits, Environmental Review
January 19, 2016 - JARPA application submitted to U.S. Army Corps of Engineers
February 12, 2016 - SEPA application submitted to Sammamish Community Development